Further testing done at Cushman No. 2 hydroelectric plant to: 1) gain further knowledge concerning relationship of clearances mortality at this prototype installation by using well-graded fish of two size groups; 2) determine if the survival rates were changed by improvement in recovery techniques; 3) gain further information on the significance of turbine characteristics to mortality, especially those associated with power loadings and operating efficiencies of the unit.